| Collegiate Sports Paging System Status Assessment Version 1.0  Revision
History 
  
    | Date | Version | Description | Author |  
    | November 22, 1999 | 1.0 | Weekly assessment | Context Integration |  Table of ContentsIntroduction PurposeThis status assessment reviews the current status of the project with respect
to resources, budget, schedule, risk, technical issues, and management issues.
Any actions arising from this assessment will be summarized in this document. ScopeThis assessment reviews all aspects of the Collegiate Sports Paging System. Definitions, Acronyms and AbbreviationsSee Glossary. References
  CSPS Vision 1.0CSPS Requirements Management Plan 1.0CSPS Iteration Plan 1.0CSPS Creative Design Brief 1.0CSPS Supplementary Specification 1.0CSPS Iteration Plan 3.0CSPS Risk List 3.0 Resources Personnel/StaffingElaboration staff will be leaving the project as they are no longer needed.
Departing staff include Brian Egler, Business Analyst, and Mark Grimes, Creative
Designer. Staff whose contribution will increase are Justin Woddis, Implementer,
various implementation subcontractors reporting to Justin, and Chris Curvey,
Tester. Financial DataThe project is delivered on a fixed-price basis. As such, no financial data
need be reported. Top 10 Risks The project risks and their mitigation strategies can be found in the Risk
List. Technical Progress During this iteration, the following artifacts were produced:
 
  User-Interface PrototypeAnalysis ModelDesign ModelSoftware Architecture DocumentIntegration Build PlanArchitectural Prototype - Software BaselineTest Drivers, Stubs, Data, & ScriptsTest ProceduresTest Evaluation ReportIteration PlanStatus AssessmentIteration AssessmentTest PlanDesign GuidelinesUser-Interface Guidelines The following artifacts were updated:
 
  GlossaryVision DocumentUse Case SpecificationsSupplementary SpecificationUse Case Model and Model SurveyProject PlanProject ScheduleProject Risk List Major Milestone Results The following table lists iteration milestones and their status at the end of
this iteration. 
  
    | Milestone | Planned | Actual | Comments |  
    | Use case design complete | 11/3/1999 | 11/4/1999 | One-day slip for documentation |  
    | Software Architecture document complete | 11/22/1999 | 11/21/1999 | No major issues raised with use cases during
    architectural design |  
    | Test Plans Complete | 11/9/1999 | 11/10/1999 | Mapped to use cases |  Total Project/Product Scope No scope changes occurred during this period. Action Items and
Follow-Through The following action items were carried forward from last week or initiated
this week: 
  
    | Item | Assigned | Due | Status |  
    | Validate color scheme for UI with advertiser
    rep. | Mark Grimes | 11/19/1999 | Closed – minor change made to UI design
    guidelines |  
    | Investigate multi-tiered gateway approach | Ken Perch | 11/25/1999 | Open |  
 
 Copyright 