Schedule development means determining start and finish dates for project activities.
If the start and finish dates are not realistic, the project is unlikely to be finished
as scheduled. The schedule development process must often be iterated (along
with the processes that provide inputs, especially duration estimating and cost estimating)
prior to determination of the project schedule.
6.4.1 Inputs to Schedule Development .1 Project network diagram. Project network diagrams are described in Section 6.2.3.1. .2 Activity duration estimates. Activity duration estimates are described in Section 6.3.3.1. .3 Resource requirements. Resource requirements are described in Section 6.3.1.4. .4 Resource pool description. Knowledge of what resources will be available at what times and in what patterns is necessary for schedule development. For example, shared or critical resources can be especially difficult to schedule since their availability may be highly variable. The amount of detail and the level of specificity in the resource pool description will vary. For example, one need only know that two consultants will be available in a particular time frame for preliminary schedule development of a consulting project. The final schedule for the same project, however, must identify which specific consultants will be available. .5 Calendars. Project and resource calendars identify periods when work is allowed. Project calendars affect all resources (e.g., some projects will work only during normal business hours while others will work a full three shifts). A five-day workweek is an example of calendar usage. Resource calendars affect a specific resource or category of resources (e.g., a project team member may be on vacation or in a training program; a labor contract may limit certain workers to certain days of the week). .6 Constraints. Constraints are factors that will limit the project management team's options. There are two major categories of time constraints considered during schedule development:
.7 Assumpions. See Section 4.1.1.5. .8 Leads and lags. Any of the dependencies may require specification of a lead or a lag in order to accurately define the relationship. An example of a lag:, there might be a desire to schedule a two-week delay (lag) between ordering a piece of equipment and installing or using it. An example of a lead, in a finish-to-start dependency with a ten-day lead: the successor activity stars ten days before the predecessor has completed. .9 Risk management plan. The risk management plan is discussed in 11.1.3. .10 Activity attributes. Attributes of the activities–including responsibility (i.e., who will perform the work), geographic area or building (where the work has to be performed), and activity type (i.e., summary or detailed)– are very important for further selection and sorting of the planned activities in a convenient way for the users. WBS classification is also an important attribute that allows useful activity ordering and sorting. 6.4.2 Tools and Techniques for Schedule Development .1 Mathematical analysis. Mathematical analysis involves calculating theoretical early and late start and finish dates for all project activities without regard for any resource pool limitations. The resulting dates are not the schedule, but rather indicate the time periods within which the activity could be scheduled given resource limits and other known constraints. The most widely known mathematical analysis techniques are:
.2 Duration compression. Duration compression is a special case of mathematical analysis that looks for ways to shorten the project schedule without changing the project scope (e.g., to meet imposed dates or other schedule objectives). Duration compression includes techniques such as:
.3 Simulation. Simulation involves calculating multiple project durations with different set of activity assumptions. The most common technique is Monte Carlo Analysis, in which a distribution of probable results is defined for each activity and used to calculate a distribution of probable results for the total project (see also Section 11.4.2.4). In addition, what-if analyses can be made using the logic network to simulate different scenarios, such as delaying a major component delivery, extending specific engeneeiring durations, or introducing external factors (such as a strike, or a change in the permiting process). The outcome of the what-if simulations can be used to assess the feasibility of the schedule under adverse conditions, and in preparing contigency/response plans to overcome or mitigate the impact of unexpected situations. .4 Resource leveling heuristics. Mathematical analysis often produces a preliminary early-start schedule that requires more resources during certain time periods than are available, or requires changes in resource levels that are not manageable. Heuristics, such as, “Allocate scarce resources to critical path activities first”, can be applied to develop a schedule that reflects such constraints. Resource leveling often results in a project duration that is longer than the preliminary schedule. This technique is sometimes called the resource-based method, especially when implemented with computerized optimization. Resource reallocation from non-critical to critical activities is a common way to bring the schedule back, or as close as possible, to its originally intended overall duration. Utilization of extended hours, weekends, or multiple shits should also be considered to reduce the durations of critical activities. Productivity incresases based on use of diferent technologies and/or machinery (i.e., automatic welding, electrical pipe cutters, etc.) are another way to shorten durations that have extended the preliminary schedule. Fact tracking, if feasible (as described in Section 6.4.2.2), is another way to reduce the overall project duration. Some projects may have a finite and critical project resource, requiring that this resource be scheduled in reverse from the project ending date; this is know as reserve resource allocation scheduling. Critical chain is a technique that modifies the project schedule to account for limited resources. .5 Project management software. Project management software is widely used to assist with schedule development. Other software may be capable of interacting directly or indirectly within themselves, or with other software, to carry out the requirements of other knowledge areas. These products automate the calculation of the mathematical analysis and resource leveling and thus allow for rapid consideration of many schedule alternatives. They are also widely used to print or display the outputs of schedule development. .6 Coding structure. The activities should have a coding structure that will allow sorting and/or extractions based on different attributes assigned to the activities, such as responsibility, geographic area or building, project phase, schedule level, activity type, and WBS classification. 6.4.3 Outputs from Schedule Development
.1 Project schedule. The project schedule includes at least planned start and
expected finish dates for each detail activity. (Note: the project
schedule remains preliminary until resource assignments have been
confirmed. This would usually happen no later than the completion of
Project Plan Development,
Section 4.1).
.2 Supporting detail. Supporting detail for the project schedule includes at least documentation of all identified assumptions and constraints. The amount of additional detail varies by application area. For example:
.3 Schedule management plan. A schedule management plan defines how changes to the
schedule will be managed. It may be formal or informal, highly detailed or
broadly framed, based on the needs of the project. It is a subsidiary
element of the overall project plan (see
Section 4.1).
.4 Resource requirement updates. Resource leveling list updates may have a
significant effect on preliminary estimates of resource requirements.
|
![]() ![]() ![]() |