Organizational planning involves identifying, documenting, and assigning project
roles, responsibilities, and reporting relationships. Roles, responsibilities, and reporting
relationships may be assigned to individuals or to groups. The individuals
and groups may be part of the organization performing the project, or they may be
external to it. Internal groups are often associated with a specific functional department
such as engineering, marketing, or accounting.
9.1.1 Inputs to Organizational Planning .1 Project interfaces. Project interfaces generally fall into one of three categories:
These interfaces often occur simultaneously, as when an architect employed by a design firm explains key design considerations to an unrelated construction contractor’s project management team. .2 Staffing requirements. Staffing requirements define what kinds of competencies are required from what kinds of individuals or groups and in what time frames. Staffing requirements are a subset of the overall resource requirements identified during resource planning (described in Section 7.1). .3 Contraints. Constraints are factors that limit the project team’s options. A project’s organizational options may be constrained in many ways. Common factors that may constrain how the team is organized include, but are not limited to, the following:
9.1.2 Tools and Techniques for Organizational Planning .1 Templates. Although each project is unique, most projects will resemble another project to some extent. Using the role and responsibility definitions or reporting relationships of a similar project can help expedite the process of organizational planning. .2 Human resource practices. Many organizations have a variety of policies, guidelines, and procedures that can help the project management team with various aspects of organizational planning. For example, an organization that views managers as “coaches” is likely to have documentation on how the role of “coach” is to be performed. .3 Organizational theory. There is a substantial body of literature describing how organizations can and should be structured. Although only a small subset of this body of literature is specifically targeted toward project organizations, the project management team should be generally familiar with the subject of organizational theory so as to be better able to respond to project requirements. .4 Stakeholder analysis. The identification of stakeholders and the needs of the various stakeholders should be analyzed to ensure that their needs will be met. Section 10.1.2.1 discusses stakeholder analysis in more detail. 9.1.3 Outputs from Organizational Planning
.1 Role and responsibility assignments. Project roles (who does what) and
responsibilities (who decides what) must be assigned to the appropriate project stakeholders.
Roles and responsibilities may vary over time. Most roles and responsibilities
will be assigned to stakeholders who are actively involved in the work of the project,
such as the project manager, other members of the project management team,
and the individual contributors.
.2 Staffing management plan. The staffing management plan describes when and how
human resources will be brought onto and taken off the project team. The staffing
plan may be formal or informal, highly detailed or broadly framed, based on the
needs of the project. It is a subsidiary element of the overall project plan (see
Section 4.1,
Project Plan Development).
.3 Organization chart. An organization chart is any graphic display of project reporting
relationships. It may be formal or informal, highly detailed or broadly framed, based
on the needs of the project. For example, the organization chart for a three- to four-person
internal service project is unlikely to have the rigor and detail of the organization
chart for a 3,000-person disaster response team. .4 Supporting detail. Supporting detail for organizational planning varies by application area and project size. Information frequently supplied as supporting detail includes, but is not limited to:
|
![]() ![]() ![]() |