Roles and Activities > Manager Role Set > Project Manager > Develop Quality Assurance Plan
Activity:
|
Purpose
|
|
Steps | |
Input
Artifacts:
|
Resulting Artifacts: |
Role: Quality/Process Manager |
Workflow Details: |
The Quality Assurance Plan is a composite document which contains all the information necessary to carry out the quality assurance activities for the project. While much of the information referenced by the Quality Assurance Plan is also referenced in the Software Development Plan, it is still important to develop both plans because they have a different purpose.
The Quality Assurance Plan is used to plan a program of reviews and audits that will check that the defined project process is being followed correctly, as defined by the various supporting plans that it references. It can be thought of as the "quality view" of the project's plans, whereas the Software Development Plan presents a "delivery view".
In this activity, the Quality/Process Manager defines and/or reviews the Quality Assurance program for appropriateness and acceptability, and coordinates with the developers of the referenced plans.
The Quality/Process Manager may not necessarily define the quality goals for the project, but ensures that these definitions are created and agreed by the customer, and captured ultimately in the Software Requirements Specification. The developing organization may also have a standard set of quality goals, in a quality policy statement, which can form the basis for these definitions.
Where possible, these objectives should be described in measurable terms. For example:
The next step is to define the organization, roles and responsibilities that will participate in these activities. This should include the reporting channel for the results of Quality Assurance reviews. In many situations, the Quality Assurance activity should submit its reports directly to the Project Review Authority. The Quality/Process Manager should have responsibility for the process aspects of quality, and perform process reviews and audits, as well as ensuring the proper planning and conduct of the review events described in the Review and Audit section of the Quality Assurance Plan. If possible, theses audits should be conducted by a person who is not member of the project development team.
The Quality Assurance Plan also references a number of other plans describing project standards and how various supporting process (e.g. configuration management) to be handled. This information is used to help determine the types of Quality Assurance reviews that will be done, and their frequency. The referenced plans would normally include:
Identify the tasks and activities of Quality Assurance. Typically these reviews would include:
The Quality/Process Manager determine
the schedule for Quality Assurance reviews and audits, and the schedule
is captured in the project and iteration plan, which may then be referenced
from the Quality Assurance Plan. The contract may also allow the customer
to request audits.