Priorizar as atividades
The WIL should be prioritized before you plan the next iteration. Consider what has changed since the last iteration
plan such as new change requests, shifting priorities of your stakeholders or new risks that have been encountered. |
Refinar o plano de Projeto e Documento de Requisitos
Depending on the results of the previous iteration assessment the Project Manager may need
to revise the Project Plan. Necessary changes can encompass the need to acquire new resources, to
absorb an unplanned effort increase, or to implement a specific change request. If a change affects defined project
milestones, the Project Manager should consult with the stakeholders before committing to them. |
Definir os objetivos da iteração
Responsabilizar os integrantes pelas tarefas
Cuidar dos riscos
Throughout the project, new assumptions and concerns may arise. The team identifies and prioritizes new risks
as part of iteration planning, updating the Risk List. Responses to
risks are added to the Work Items List,
influencing the work that is being planned for that iteration.
|
Definir os critérios de avaliação
Each iteration should include testing as a part of the evaluation, and the test objectives and test cases
that need to be detailed. Other evaluation criteria may include successful demonstrations to key stakeholders, or
favorable usage by a small group of target users. Document evaluation criteria in the Iteration Plan.
|
|